G.O. Bond Park Projects

SOUTHEAST PARK IMPROVEMENTS
TURF SOCCER FIELDS & NEW PLAYGROUND (PHASE I)
AS OF DATE STATUS
DESIGN 6/05/2019 100%
PERMITTING 10/1/2019 100%
CONSTRUCTION 2/24/2020 100%
FINAL CLOSEOUT / GRANT REIMBURSEMENT
4/12/2020 100%
SOUTHEAST PARK IMPROVEMENTS
TURF SOCCER FIELDS & PARKING IMPROVEMENTS (PHASE II)
AS OF DATE STATUS
DESIGN 12/1/2024 100%
PERMITTING 2/1/2025 100%
CONSTRUCTION 5/23/2025 100%
FINAL CLOSEOUT / GRANT REIMBURSEMENT 9/4/2025 95%
CALYPSO COVE PARK IMPROVEMENTS
FACILITY IMPROVEMENTS 
AS OF DATE STATUS
DESIGN 2/24/2020 100%
PERMITTING 12/1/2024 100%
CONSTRUCTION 3/15/2025 100%
FINAL CLOSEOUT / GRANT REIMBURSEMENT
3/15/2025 100%
SPORTS FIELD LED LIGHTING IMPROVEMENTS  
SPORTS COMPLEX / SOUTHEAST PARK   
    AS OF DATE
STATUS
DESIGN 1/13/2020 100%
PERMITTING 1/13/2020 100%
CONSTRUCTION 2/24/2020 100%
FINAL CLOSEOUT / GRANT REIMBURSEMENT
5/12/2020 100%
VINSON PARK RENOVATIONS         DATE  STATUS
DESIGN 5/12/2020 100%
PERMITTING 5/12/2020 100%
CONSTRUCTION 1/11/2022 100%
FINAL CLOSEOUT / GRANT REIMBURSEMENT 3/1/2022 100%
ORIOLE PARK RENOVATIONS - THIS PROJECT HAS BEEN PAUSED                   DATE STATUS
DESIGN 11/8/2021 100%
PERMITTING 1/11/2022 50%
CONSTRUCTION TBD N/A
FINAL CLOSEOUT / GRANT REIMBURSEMENT  TBD N/A
CENTENNIAL PARK RENOVATION - PROJECT OUT FOR BID DATE  STATUS 
DESIGN TBD N/A
PERMITTING TBD N/A
CONSTRUCTION TBD N/A
FINAL CLOSEOUT / GRANT REIMBURSEMENT TBD N/A