G.O. Bond Park Projects

SOUTHEAST PARK IMPROVEMENTS
TURF SOCCER FIELDS & NEW PLAYGROUND
AS OF DATE
STATUS
DESIGN 6/05/2019 100%
PERMITTING 10/1/2019 100%
CONSTRUCTION 2/24/2020 100%
FINAL CLOSEOUT / GRANT REIMBURSEMENT
4/12/2020 100%
CALYPSO COVE PARK IMPROVEMENTS
LAZY RIVER - PROJECT HAS BEEN PAUSED
AS OF DATE STATUS
DESIGN 2/24/2020 30%
PERMITTING TBD 0%
CONSTRUCTION TBD 0%
FINAL CLOSEOUT / GRANT REIMBURSEMENT
TBD 0%
SPORTS FIELD LED LIGHTING IMPROVEMENTS  
SPORTS COMPLEX / SOUTHEAST PARK   
    AS OF DATE
STATUS
DESIGN 1/13/2020 100%
PERMITTING 1/13/2020 100%
CONSTRUCTION 2/24/2020 100%
FINAL CLOSEOUT / GRANT REIMBURSEMENT
5/12/2020 100%
VINSON PARK RENOVATIONS         DATE  STATUS
DESIGN 5/12/2020 100%
PERMITTING 5/12/2020 100%
CONSTRUCTION 1/11/2022 100%
FINAL CLOSEOUT / GRANT REIMBURSEMENT 3/1/2022 100%
ORIOLE PARK RENOVATIONS                          DATE STATUS
DESIGN 11/8/2021 100%
PERMITTING 1/11/2022 50%
CONSTRUCTION TBD N/A
FINAL CLOSEOUT / GRANT REIMBURSEMENT  TBD N/A
CENTENNIAL PARK RENOVATION DATE  STATUS 
DESIGN 11/8/2021 100%
PERMITTING 1/11/2022 50%
CONSTRUCTION TBD N/A
FINAL CLOSEOUT / GRANT REIMBURSEMENT TBD N/A