SOUTHEAST PARK CONCESSION PROJECT |
DATE |
STATUS |
---|---|---|
DESIGN | N/A | 100% |
PERMITTING | 8/15/2019 | 100% |
CONSTRUCTION | 9/16/2019 | 90% |
FINAL CLOSEOUT / GRANT REIMBURSEMENT |
10/1/2019 | 33% |
VETERANS PARK / MARINA RESTROOM PROJECT |
DATE | STATUS |
---|---|---|
DESIGN | N/A | 100% |
PERMITTING | 9/2019 | 100% |
CONSTRUCTION | 9/2019 | 75% |
FINAL CLOSEOUT / GRANT REMIBURSEMENT | 10/31/2019 | 0% |
FIREFIGHTERS PARK PROJECT ($200,000 GRANT) |
DATE | STATUS |
---|---|---|
DESIGN | 3/1/2019 | 100% |
PERMITTING | 5/29/2019 | 100% |
CONSTRUCTION | 6/24/2019 | 95% |
FINAL CLOSEOUT / GRANT REIMBURSEMENT |
10/6/2019 | 25% |
DOG PARK PROJECT |
DATE |
STATUS |
---|---|---|
DESIGN | 7/10/2019 | 90% |
PERMITTING | TBD | 0% |
CONSTRUCTION | TBD | 0% |
FINAL CLOSEOUT / GRANT REIMBURSEMENT |
TBD | 0% |
BLUEWAY TRAIL PROJECT ($200,000 GRANT) |
DATE | STATUS |
---|---|---|
DESIGN | 7/2019 | 30% |
PERMITTING | TBD | 0% |
CONSTRUCTION | TBD | 0% |
FINAL CLOSEOUT / GRANT REIMBURSEMENT |
TBD | 0% |
SOUTHGATE PARK PROJECT ($200,000 GRANT) |
DATE |
STATUS |
---|---|---|
DESIGN |
9/1/2019 | 90% |
PERMITTING | TBD | 0% |
CONSTRUCTION | TBD | 0% |
FINAL CLOSEOUT / GRANT REIMBURSEMENT |
TBD | 0% |